Nuclear Timeline
A History of Nuclear Innovation
Fluor's nuclear experience goes back to the early days of atomic energy. Starting in 1946, Fluor designed and constructed numerous facilities to support the U.S. Atomic Energy Commission / U.S. Department of Energy. In 1970, Fluor entered the commercial nuclear business by constructing Alabama Power's Farley Nuclear Plant. Since 1977, Fluor has provided operating plant support services to 90 U.S. and international nuclear units.
In 1992, Fluor began performing nuclear decommissioning and environmental cleanup services to the U.S. Department of Energy's nuclear sites. By investing in NuScale Power, Fluor continues to support nuclear innovation and development.
1940s
Fluor begins designing and constructing facilities in support of the U.S. Atomic Energy Commission (AEC).
1946
U.S. Atomic Energy Commission contracts Fluor to support nuclear project

1946: U.S. Atomic Energy Commission contracts Fluor to support nuclear project

Starting in 1946, Fluor designed and/or constructed numerous facilities in support of AEC, later the U.S. Department of Energy (DOE), nuclear weapons complex.
1946
Fluor recognized for efforts in nuclear industry

1946: Fluor recognized for efforts in nuclear industry

Fluor was recognized for their Chemical Engineering Achievements in the nuclear industry. Fluor entered the atomic field indirectly when the company installed enormous banks of cooling towers to serve the needs of a diffusion plant.
1950s
Fluor provides research and development support for the AEC as a member of the Rocky Mountain Nuclear Power Study Group.
1952
Fluor constructs Materials Testing Reactor for the AEC

1952: Fluor constructs Materials Testing Reactor for the AEC

Fluor served as the major construction contractor for the AEC's Materials Testing Reactor, which was completed in 1952.
1955
Fluor researches the economic possibilities of a nuclear reactor

1955: Fluor researches the economic possibilities of a nuclear reactor

In 1955, Fluor was named by the AEC as one of the Rocky Mountain Nuclear Power Study Group members. The Rocky Mountain Nuclear Power Study Group was comprised of nine U.S. firms. As part of the Group, Fluor entered into an agreement with AEC to engage in non-profit research into the economic possibilities of a nuclear reactor for the generation of electric power and the utilization and disposal of its end-products.
1960s
Fluor is designated as the prime contractor for the AEC's experimental organic cooled reactor.
1960
AEC retains Fluor for Experimental Organic Cooled Reactor

1960: AEC retains Fluor for Experimental Organic Cooled Reactor

In 1960, the Atomic Energy Commission retained Fluor as prime contractor for the architect-engineering of the Experimental Organic Cooled Reactor (EOCR). The company took responsibility for a greater portion of nuclear design than had any previous architect and engineering contractor. Fluor designed and/or wrote the purchase specifications for all EOCR equipment, except fuel elements and control rods.
1963
EOCR project completed

1963: EOCR project completed

Fluor completed the project for the Atomic Energy Commission's Experimental Organic Cooled Reactor.
1967
Fluor engineers Kewaunee Nuclear Power Plant's 556-megawatt (MW) Westinghouse reactor

1967: Fluor engineers Kewaunee Nuclear Power Plant's 556-megawatt (MW) Westinghouse reactor

Fluor engineers Kewaunee Nuclear Power Plant's 556 MW Westinghouse reactor.
As the plant's original architect-engineer and construction manager, Fluor began engineering on the 556 MW Westinghouse two-loop pressurized water reactor in 1967.
1970s
Fluor continues to grow in the commercial nuclear market by offering self-perform construction for power stations.
1970
Construction begins for Alabama Power Company’s 1,720 MW Farley Nuclear Plant

1970: Construction begins for Alabama Power Company’s 1,720 MW Farley Nuclear Plant

Fluor signed an agreement with the Alabama Power Company to construct units 1 and 2 of the Joseph M. Farley Nuclear Plant. The 1,720 MW power plant is located in Dothan, Alabama.
1971
U.S. government decides to build modern plutonium facility in Los Alamos for research and development

1971: U.S. government decides to build modern plutonium facility in Los Alamos for research and development

Fluor engineered the TA-55 site plutonium processing facilities at the DOE site in Los Alamos, New Mexico.
1973
Shearon Harris Nuclear Station's construction project begins

1973: Shearon Harris Nuclear Station's construction project begins

Fluor performed the construction of the Shearon Harris Nuclear Plant on an open-shop basis for Carolina Power & Light. The plant is located 20 miles southwest of Raleigh, North Carolina. The project began in 1973. Following a delay due to economic conditions, the one unit 900 MW plant was completed in 1986.
1974
Fluor acquires Pioneer

1974: Fluor acquires Pioneer

Fluor acquired Pioneer, a services and engineering company, to enter the commercial nuclear architecture and engineering business.
1974
Kewaunee Nuclear Power Plant fully operable

1974: Kewaunee Nuclear Power Plant fully operable

Fluor provided engineering and design services, licensing assistance, construction management, cost and schedule control, document control, quality assurance, quality control, and start-up assistance for the 556 MW unit. After the start of commercial operation in 1974, Fluor continued to provide engineering and estimating services for alternative designs in plant modification and optimization.
Fluor engineered other major plant projects at Kewaunee including a new security system, plant computer replacement, Bulletin 79-01 component replacements, Bulletin 79-14 piping review, Three Mile Island-required modifications, and Appendix R fire protection and modifications. Fluor also provided onsite personnel during refueling outages and pre-operational testing.
1975
Fluor commences work with Detroit Edison

1975: Fluor commences work with Detroit Edison

Fluor performed quality assessments and inspections at Detroit Edison's Fermi plant.
1977
Alabama Power Company selects Fluor to provide maintenance services at Farley
&w=3840&q=75)
1977: Alabama Power Company selects Fluor to provide maintenance services at Farley
&w=3840&q=75)
Fluor began a maintenance contract with Alabama Power Company on the Joseph M. Farley Nuclear Plant as the on-site contractor and in-service inspection support. Fluor also completed mechanical modifications, scrubber inspection, modification of steam generator demister, and replaced the CWD impellers.
1978
Northern States' Prairie Island Nuclear Generating 550 MW Westinghouse reactors designed by Fluor

1978: Northern States' Prairie Island Nuclear Generating 550 MW Westinghouse reactors designed by Fluor

As the plant's original architect/engineer, Fluor provided engineering and procurement services for the two 550 MW Westinghouse two-loop pressurized water reactors at the Prairie Island Nuclear Generating Plant. Fluor also performed licensing and preoperational testing support for the units. During construction, Fluor provided cost and schedule control and start-up assistance. After start-up, Fluor offered maintenance support on an as-needed basis to the operating plant for modifications.
1979
Nuclear industry's first steam generator replacement occurs at Surry

1979: Nuclear industry's first steam generator replacement occurs at Surry

Fluor provided primary contracting services to replace six steam generators at the Surry Power Station. This project was the first of its type performed in the nuclear industry. The plant consisted of two 822 MW units incorporating a closed-cycle pressurized water nuclear steam supply system. The replacement program was designed to restore the six steam generators to new condition.
In addition to the steam generator replacements, Fluor performed a multiphase construction and repair program. Major modifications were made to the condensers, the condensate polishing system, the makeup water system, the containment cooling system, the auxiliary building ventilation, and the containment spray system.
1980s
Fluor deploys a large staff of experienced nuclear professionals to the field to operate and maintain nuclear plants for customers throughout the U.S.
1982
Fluor contracted for backfit engineering for 860 MW reactor at Crystal River 3

1982: Fluor contracted for backfit engineering for 860 MW reactor at Crystal River 3

Fluor was the on-site contractor selected to provide backfit engineering, modification, and maintenance at Florida Power Corporation's Crystal River 3 plant. Fluor's services to the 860 MW pressurized water reactor facility included project management, field engineering, planning, scheduling, cost control, craft supervision, and provision of skilled craftsmen.
1982
V.C. Summer Nuclear Power Station facility turnover and fuel loading performed

1982: V.C. Summer Nuclear Power Station facility turnover and fuel loading performed

In August 1982, turnover of facilities and systems to South Carolina Electric & Gas Company was completed and fuel loading performed. The $1.3 billion plant was placed into commercial operation in October 1983. Fluor performed construction of this 900-MW pressurized water reactor nuclear plant located near Columbia, South Carolina. The plant uses a Westinghouse nuclear steam supply system and a General Electric turbine generator.
1983
V.C. Summer Nuclear Power Station's cooling water pumped from Fairfield Hydroelectric Power Station's reservoir

1983: V.C. Summer Nuclear Power Station's cooling water pumped from Fairfield Hydroelectric Power Station's reservoir

Fluor self-performed the construction and equipment installation at South Carolina Electric & Gas Company's Fairfield Pumped-Storage Hydroelectric Power Station. The 511-MW facility is operated in conjunction with the V.C. Summer Nuclear Power Plant. The facility's upper impoundment, known as the Monticello Reservoir, covers 6,800 acres and provides cooling water for the nuclear facility.
1983
Fluor designs high-level nuclear waste repository in salt

1983: Fluor designs high-level nuclear waste repository in salt

Fluor was the prime contractor for the design of a high-level nuclear waste repository in a geologic salt medium for the DOE. Fluor provided conceptual designs for both surface and subsurface facilities. Facility functions included receiving, unloading, inspecting, packaging, transporting and emplacing spent fuel, high-level nuclear waste, remotely handled transuranic waste, and contact-handled transuranic waste.
1984
1150 MW Callaway Nuclear Power Generating Plant operational

1984: 1150 MW Callaway Nuclear Power Generating Plant operational

Fluor built the 1,150 MW Callaway Nuclear Power Plant using the Standardized Nuclear Unit Power Plant System concept. It required more than 40,000 drawings from design engineers and 50,000 drawings from vendors. The complexity and extent of the quality control and regulatory compliance procedures are reflected in the involvement of more than 50 federal, state, and local agencies.
Fluor executed the work under a project agreement with the local building trades, except for pipefitter craftwork, which was completed by Fluor. Fluor's staff onsite exceeded 2,700 craft and 1,200 on-site engineers, technicians, and staff.
1984
Fluor TXU Partnering Alliance Commences

1984: Fluor TXU Partnering Alliance Commences

The Fluor / TXU Partnering Alliance contract included services at 23 fossil stations, and an expanded scope of maintenance and modifications at the Comanche Peak Nuclear Power Plant.
1984
Detroit Edison Company begins operations at Fermi

1984: Detroit Edison Company begins operations at Fermi

Fluor was contracted by Detroit Edison Company to engineer and manage construction for the Enrico Fermi Nuclear Power Plant. Fluor was also responsible for the project cost and scheduling, warehousing operations, site quality control and inspection, project safety program administration, and administration of the project labor agreement. Furthermore, Fluor provided records verification, record retention, and other related services in accordance with Detroit Edison's Quality Program. Fluor developed and conducted a quality training program for the facility personnel.
In June 1984, the turnover of the Fermi facilities and systems to the client's operating department was completed. Subsequently, Fluor continued to provide engineering and construction services on a task order basis.
1985
Contract for EPC commences for San Onofre

1985: Contract for EPC commences for San Onofre

Beginning in 1984, Fluor provided various services on a task by task basis to Southern California Edison Company in connection with the San Onofre Nuclear Generating Station (SONGS). SONGS consists of three units. Unit 1 is a 436 MW, Westinghouse three loop PWR type nuclear power plant, which began commercial operation in 1968. Units 2 and 3 are 1,100 MW, two steam generator combustion engineering PWR type nuclear power plants, which began commercial operation in 1983 and 1984 respectively. Fluor’s services on site included engineering, procurement, construction, studies and consulting.
1985
H.B. Robinson maintenance and modifications supported by Fluor

1985: H.B. Robinson maintenance and modifications supported by Fluor

Fluor provided maintenance and modification services at the Carolina Power & Light (CP&L) H.B. Robinson Nuclear Plant to support ongoing operations and outages. A wide range of quality personnel also were provided. They were tested and certified in accordance with CP&L's quality program, complimenting previous Fluor certifications. Fluor also provided a full range of multidiscipline personnel in support of a steam generator replacement effort.
1986
Fluor constructs record-setting 1150-MW nuclear power plant at Wolf Creek

1986: Fluor constructs record-setting 1150-MW nuclear power plant at Wolf Creek

Fluor built the record-setting 1,150 MW nuclear power generating station for Wolf Creek Nuclear Operating Company. The total program, from groundbreaking to fuel loading, spanned more than eight years.
The project’s construction initiated in 1977 and reached commercial operation in 1986. In its first year of operation, Wolf Creek produced 8,926,510 MW of electrical energy – a production record for the 29-year history of nuclear power generation.
1986
Virginia Power hires Fluor to implement design change modifications at North Anna

1986: Virginia Power hires Fluor to implement design change modifications at North Anna

Fluor began a full-time presence at North Anna in 1986. Fluor was responsible for implementing all design change modifications at these units. Fluor also provided associated support services for modifications implementation as requested by the client, including supplemental non-destructive examination.
1986
Fluor provides engineering services for Millstone in Waterford, Connecticut
&w=3840&q=75)
1986: Fluor provides engineering services for Millstone in Waterford, Connecticut
&w=3840&q=75)
Fluor was the site engineering contractor for Northeast Utilities' Millstone Nuclear Power Station in Waterford, Connecticut.
1986
Fluor designs uranium enrichment facility at Portsmouth
&w=3840&q=75)
1986: Fluor designs uranium enrichment facility at Portsmouth
&w=3840&q=75)
For DOE's Gas Centrifuge Enrichment Plant (GCEP), one of the largest Government construction projects ever undertaken, Fluor was responsible for Title I, II, and III design, engineering, and construction support services for all process facilities. These facilities, which included eight process buildings, four process support buildings, a central control building, a feed and withdrawal building and over 7,000 feet of interconnecting process pipeways, were designed for the enrichment of uranium hexafluoride at a rate of 13.2 million SWU's per year. Although the GCEP Program was cancelled in its entirety by Act of Congress in 1985, Fluor's engineering activity was essentially complete and construction efforts were well underway.
1989
Fluor completes construction support at Comanche Peak
&w=3840&q=75)
1989: Fluor completes construction support at Comanche Peak
&w=3840&q=75)
Fluor's construction at Comanche Peak involved the complete rework of the plant's HVAC and fire protection system and assistance to the original constructor in reworking electrical supports. Fluor provided a number of professionals to integrate within the TXU organization to support plant completion and initial operations.
1990s
Fluor offers a range of services from design-build to decontamination and decommissioning at U.S. Department of Energy sites around the nation.
1990
Fluor begins conceptual design of Special Nuclear Materials Research and Development lab replacement at Los Alamos
&w=3840&q=75)
1990: Fluor begins conceptual design of Special Nuclear Materials Research and Development lab replacement at Los Alamos
&w=3840&q=75)
Fluor's scope included the conceptual and final design of a 193,000-square-foot facility consisting of a hardened Plutonium Processing Laboratory, an adjoining Support Laboratory and Change Room Building, a three-story Office Building and Waste Pretreatment Facility. In addition, a personnel entrance Portal/Guard Station was designed to resist the high power rifle requirement per U.L. standard. The purpose of this complex was to perform plutonium analytical and processing chemistry and metallurgy activities.
1990
Fluor reviews new modular high temperature gas-cooled reactor

1990: Fluor reviews new modular high temperature gas-cooled reactor

Fluor reviewed the modular high temperature gas-cooled reactor's (MHTGR) ability to simultaneously produce tritium and large amounts of steam for efficient conversion to approximately 1,100 MW of electric power. The report was prepared for the New Production Reactor program.
Fluor determined that the MHTGR could provide the electrical power industry with invaluable experience in the operation of an intrinsically safe nuclear reactor.
1991
Fluor contracted to provide AE services for MHTGR Fuel and Target Fabrication Facilities

1991: Fluor contracted to provide AE services for MHTGR Fuel and Target Fabrication Facilities

The Fuel and Target Fabrication Facilities (FTFF) were to fabricate fuel and target element assemblies for use in the production of tritium via four MHTGR modules.
The FTFF facility consisted of fuel, target, operations, and service buildings. To translate the process design requirements into integrated fuel and target production lines, an interface was established with the process demonstration contractors. Fluor contributed to the process technology and equipment design and provided building and utility designs. Tasks included optimization of building arrangement, identification of process/support systems, layout of functional process equipment, and layout of receipt and handling of head-end materials, in-process materials, and loaded fuel and target elements.
1991
Fluor nuclear maintenance contract renewed at Crystal River

1991: Fluor nuclear maintenance contract renewed at Crystal River

Fluor provided maintenance and modification services through a permanent site-based staff. Personnel resources were drawn from Fluor to meet the fluctuating demands of the plant. Fluor's first maintenance contract at Florida Power Corporation's Crystal River nuclear plant began in 1983.
1992
Fluor leads environmental restoration at Fernald for U.S. DOE

1992: Fluor leads environmental restoration at Fernald for U.S. DOE

Throughout the Cold War, the Fernald site delivered high-grade uranium metal products for the nuclear weapons complex. In 1992, Fluor began managing the environmental restoration of the site, one of the largest environmental cleanup operations undertaken in U.S. history.
1992
Fluor designs Hanford Waste Vitrification Plant

1992: Fluor designs Hanford Waste Vitrification Plant

Fluor designed the Hanford Waste Vitrification Plant (HWVP) to immobilize liquid nuclear defense waste in borosilicate glass for compliance with all current quality standards. Fluor also performed Title I engineering services.
The HWVP facility is a multi-building complex designed to immobilize 100 lbs /hr of high-level nuclear defense waste. The facilities are designed to comply with DOE regulations, and have an operating design life of 40 years. Operational availability was designed for 70% minimum, excluding the meter replacement. Critical components were designed to withstand the effects of severe and extreme environmental loads. Fluor’s design emphasized the importance of safety, economy, operability, maintenance, decontamination, and decommissioning.
1992
Fluor completes DOE Nuclear Weapons Complex Reconfiguration Study and begins engineering work

1992: Fluor completes DOE Nuclear Weapons Complex Reconfiguration Study and begins engineering work

After the Cold War, the DOE initially proposed to reconfigure the Nuclear Weapons Complex to be smaller, less diverse, and less expensive than the existing complex, as described in the January 1991 DOE Nuclear Weapons Complex Reconfiguration Study. Due to significant changes, the nuclear Weapons Complex Reconfiguration Program (WCRP) was separated into: tritium supply and recycling; stockpile stewardship and management; and storage and disposition of weapons - usable fissible materials. Fluor provided A-E services to the DOE on the nuclear WCRP including conceptual design work, feasibility studies, cost estimates, Environmental Impact Study support, safety analyses, and other tasks.
1992
Nuclear fuel processing facility modifications completed at Hanford

1992: Nuclear fuel processing facility modifications completed at Hanford

Fluor performed detailed design of a nuclear fuel reprocessing facility at the DOE Hanford Reservation. The Process Facility Modifications project provided a new mechanical head end capability for the existing Plutonium-Uranium Reduction Extraction (PUREX) Plant. The Process Facility Modifications replaced the chemical decladding and dissolution steps which were previously used in the PUREX plant.
1993
Millstone Unit 2 steam generator replacement performed by Fluor

1993: Millstone Unit 2 steam generator replacement performed by Fluor

Fluor provided engineering, construction, quality assurance, and procurement services for the replacement of the steam generators on Unit 2 of the Millstone Power Station.
Replacement of the steam generators consisted of cutting each of two CE steam generators in half, removing the lower assembly through the existing equipment hatch, replacing steam drum internals, bringing in two new B&W replacement lower assemblies, and welding the lower assemblies back to the steam drums. Work included the modification of the polar crane as well as miscellaneous interference relocations and facilities support. Extensive use was made of mock-up training and photogrammetry.
1993
Fluor supports Idaho National Engineering Lab

1993: Fluor supports Idaho National Engineering Lab

Fluor provided architectural and engineering services to the Idaho National Engineering Laboratory to upgrade, modernize, and improve existing facilities at the Idaho Chemical Processing Plant (ICPP). Over the five year contract period, Fluor was available on short notice for any assignment, large or small.
As part of this contract, Fluor provided conceptual design services for the NOx Abatement Project for the ICPP. The project provided a facility to reduce NOx emissions from the New Waste Calcining Facility off-gas. Selective Catalytic Reduction type NOx abatement equipment, with a design goal of 99 percent removal, was selected as the candidate process.
1995
Fluor awarded contract for Canister Storage Building at Hanford
&w=3840&q=75)
1995: Fluor awarded contract for Canister Storage Building at Hanford
&w=3840&q=75)
Fluor designed, constructed, and operated the Canister Storage Building (CSB). CSB provides interim storage for spent nuclear fuel removed from the K Basins adjacent to the Columbia River. The CSB received containers [Multi-Canister Overpacks (MCOs)] of dried spent fuel from the Cold Vacuum Drying Facility. The MCOs are stored in below-grade tubes, and provide safe storage and surveillance of the fuel for 40 years or more. Fluor completed seal welding the MCOs 3 months ahead of schedule, without a single safety incident, a significant conduct of operations discrepancy, or any defective welds.
1996
Environmental remediation supported by Fluor at DOE Hanford site
&w=3840&q=75)
1996: Environmental remediation supported by Fluor at DOE Hanford site
&w=3840&q=75)
Fluor's environmental cleanup at Hanford began in 1996. Fluor is currently a fee-sharing subcontractor to CH2M Hill Plateau Remediation Company (PRC). PRC is performing the deactivation and decommissioning of facilities and environmental cleanup at the site in Hanford, Washington.
1996
DOE awards Fluor the management and operations prime contract at the Hanford site
&w=3840&q=75)
1996: DOE awards Fluor the management and operations prime contract at the Hanford site
&w=3840&q=75)
From 1996 - 2008, Fluor was the DOE's prime contractor ($9.5 billion contract) for remediating a significant portion of Hanford. Fluor was recognized for innovative approaches to technical challenges, safety, and community commitment.
1997
Hanford spent nuclear fuel contract awarded to Fluor by DOE
&w=3840&q=75)
1997: Hanford spent nuclear fuel contract awarded to Fluor by DOE
&w=3840&q=75)
Fluor designed, constructed, and operated first-of-a-kind equipment and processes within the existing K-Basin facilities to safely move 2,100 metric tons of spent nuclear fuel (SNF), containing 50 million curies, out of the basins and away from the Columbia River. The Fuel Retrieval and Transfer Systems were the first steps to safe removal and transfer of SNF from the K-Basins by way of the Cold Vacuum Drying Facility to interim storage in the Canister Storage Building on Hanford's Central Plateau. The work involved moving 7,200 empty fuel canisters, 7,600 canister lids, and 105,000 fuel assemblies. The project was completed in October 2004.
1997
Fernald On-Site Disposal Facility built

1997: Fernald On-Site Disposal Facility built

The DOE and Fluor developed a balanced waste management strategy that saved $1.5 billion in disposal and transportation costs by constructing a 3-million cubic yard On-Site Disposal Facility (OSDF) to hold 77% of the site’s contaminated soil and demolition debris rather than transporting the waste to offsite disposal facilities. Fluor was instrumental in securing necessary regulatory waivers to allow construction of the facility in a sensitive environment above a sole-source groundwater aquifer. Fluor designed, constructed and operated the 8-cell, lined and capped facility in compliance with stringent hazardous waste and radiological waste requirements. The OSDF resulted in dramatic cost savings and project acceleration at Fernald.
1998
Waste Receiving and Processing Facility receives authorization for start-up from DOE
&w=3840&q=75)
1998: Waste Receiving and Processing Facility receives authorization for start-up from DOE
&w=3840&q=75)
Fluor planned and managed the construction completion of the 51,000-square foot Waste Receiving and Processing (WRAP) facility, overseeing work performed by more than 200 vendors and 12 primary subcontractors. WRAP was Hanford's first major solid waste processing facility and the first at any DOE site built specifically to prepare transuranic waste for disposal at the Waste Isolation Pilot Plant in New Mexico.
1999
Fluor completes Safe Shutdown Project at Fernald
&w=3840&q=75)
1999: Fluor completes Safe Shutdown Project at Fernald
&w=3840&q=75)
When Fernald completed its uranium production mission, many uranium- and thorium-contaminated production facilities, still contained quantities of raw, intermediate, and finished uranium products. Nuclear material from the plants had to be removed in preparation for demolition. Within 6 years, Fluor completed the Safe Shutdown Project at Fernald. Completion of the project was the first within the DOE complex for a major facility undergoing remediation under the Comprehensive Environmental Response, Compensation and Liability Act. Fluor also developed the first DOE interim action Record of Decision to decouple dismantlement decisions from final waste disposal decisions, resulting in the acceleration of building demolition, the elimination of contamination sources, and significant savings in maintenance and disposal costs.
2000s
Fluor performs challenging and complex nuclear remediation and environmental cleanup for DOE facilities.
2000
Cold Vacuum Drying Facility at Hanford operational
&w=3840&q=75)
2000: Cold Vacuum Drying Facility at Hanford operational
&w=3840&q=75)
Fluor designed, constructed and operated the Cold Vacuum Drying Facility (CVDF), a $104 million first-of-a-kind structure and the newest DOE nuclear process facility in the nation. The drying operation conducted in the facility was also the first of its kind in the world to be performed on large quantities of solid metal, irradiated fuel. The CVDF is a 12,000-square foot, two-story steel frame structure with attached, pre-stressed concrete panels on a concrete operating deck. The building consists of five bay areas, two with process equipment to remove water from containerized spent fuel, two spare process areas, and one with water conditioning and load-out equipment.
2002
Fluor stabilizes and replaces plutonium-bearing materials at Hanford
&w=3840&q=75)
2002: Fluor stabilizes and replaces plutonium-bearing materials at Hanford
&w=3840&q=75)
Fluor designed, constructed, and commissioned a plutonium Stabilization and Handling System that was successfully integrated into Hanford's Plutonium Finishing Plant. The system incorporated nine thermal stabilization and 4 packaging technologies to reduce risks associated with the handling and packaging of nearly 18 metric tons of plutonium-bearing materials.
This project was nominated by the DOE customer for the DOE Complex Project of the Year, received the DOE Secretarial Award for Achievement, and was the PMI 2004 "Project of the Year." The project was completed in 2004.
2006
Physical completion of Fernald declared

2006: Physical completion of Fernald declared

On this 14-year project, Fluor managed one of the largest nuclear clean-up efforts in U.S. history, completing the project 12 years early and nearly $8 billion below initial estimates. Fluor declared physical completion of Fernald on October 29, 2006, two months ahead of the even accelerated target schedule.
2008
Fluor-led partnership selected to manage operations at the DOE's Savannah River Site

2008: Fluor-led partnership selected to manage operations at the DOE's Savannah River Site

Savannah River Nuclear Solutions, LLC is a Fluor-led partnership responsible for the management and operations of the DOE’s Savannah River Site, including the Savannah River National Laboratory, located near Aiken, South Carolina.
2010s
Fluor increases focus on nuclear research and development and new build and existing reactor capital projects and maintenance.
2010
Fluor supports nuclear remediation at Oak Ridge's K-33 building

2010: Fluor supports nuclear remediation at Oak Ridge's K-33 building

As part of the LATA Sharp Remediation Services team, Fluor supported the demolition and disposition of the U.S. Department of Energy's Oak Ridge nuclear reservation K-33 facility.
2010
Fluor leads decontamination and decommissioning at Portsmouth
&w=3840&q=75)
2010: Fluor leads decontamination and decommissioning at Portsmouth
&w=3840&q=75)
Fluor was awarded the contract to decontaminate and decommission the former uranium enrichment plant in 2010. Leading a team of contractors and a workforce of approximately 2,000, Fluor is responsible for removing process equipment, preparing structures totaling more than 10 million square feet for demolition, and constructing an on-site waste disposal facility at DOE’s Portsmouth Gaseous Diffusion Plant in Pike County, Ohio.
2011
LATA Sharp Bethel Valley's contaminated soil and legacy waste removed

2011: LATA Sharp Bethel Valley's contaminated soil and legacy waste removed

Fluor was a subcontractor to LATA Sharp Remediation Services on a task order to perform environmental management on the Oak Ridge National Laboratory site.
2011
Fluor announces significant investment in NuScale Power, LLC

2011: Fluor announces significant investment in NuScale Power, LLC

NuScale Power, LLC is an Oregon-based company that specializes in small modular reactor (SMR) technology. With the investment, Fluor became NuScale's majority shareholder. The combination of Fluor’s world class engineering, procurement, and construction expertise and NuScale’s passively safe and economical SMR technology, positions both companies as global leaders in the global new-build nuclear market.
2013
PG&E honors Fluor with Supplier of the Year award
&w=3840&q=75)
2013: PG&E honors Fluor with Supplier of the Year award
&w=3840&q=75)
Under a five-year contract, Fluor provides support for site services, facility maintenance, strategic and station projects, engineering services, and outage services at Diablo Canyon Nuclear Power Plant, which produces approximately 2,300 MW of power. In 2013, Fluor was honored to be named PG&E’s Generation Supplier of the Year for this work.
2013
DOE Awards funding for NuScale Power's SMR Technology

2013: DOE Awards funding for NuScale Power's SMR Technology

This project represents a significant investment in first-of-a-kind engineering and design certification for small modular reactors in the United States. Through a five-year cost-share agreement, the DOE will invest up to half of the total project cost with the project’s industry partners matching this investment by at least one-to-one. The specific total will be negotiated between the DOE and NuScale and will be derived from the total $452 million identified for the Department’s Small Modular Reactor Licensing Technical Support program.
2013
Savannah River Nuclear Solutions sets waste shipping record
&w=3840&q=75)
2013: Savannah River Nuclear Solutions sets waste shipping record
&w=3840&q=75)
The Savannah River Nuclear Solutions Solid Waste Organization completed 32 transuranic waste shipments during one month, including nine shipments within one week, breaking a 12-year record at the site. This waste required the design, manufacture, and certification of specialized shipping casks.
2014
NuScale completes the first round of helical coil steam generator testing

2014: NuScale completes the first round of helical coil steam generator testing

In February 2014, NuScale completed the first round of its helical coil steam generator (HCSG) testing activities at the SIET S.p.A. facilities in Pacenza, Italy. NuScale aimed to accomplish the following in the testing: Design and test a system to ensure that steam generator operation is stable. Provide ample data on the full range of operation, to benchmark NuScale HCSG computer codes and models. Measure steam generator outlet conditions as a function of primary and secondary system conditions and the tube geometry.
2014
Cavendish Fluor Partnership selected as preferred bidder for Magnox project

2014: Cavendish Fluor Partnership selected as preferred bidder for Magnox project

In 2014, Fluor's joint venture with Cavendish Nuclear was selected as the preferred bidder in the competition to take ownership of Magnox Ltd and Research Sites Restoration Limited, the Site License Companies that manage and operate 12 nuclear sites in the UK. Magnox Ltd is responsible for decommissioning 10 Magnox reactor sites, located in England, Scotland and Wales, which were the first generation of civil nuclear power plants in the UK built during the 1950s and 60s. RSRL is responsible for decommissioning two pioneering nuclear research centers at Harwell and Winfrith.
2015
Fluor performs environmental remediation at Paducah's Gaseous Diffusion Plant

2015: Fluor performs environmental remediation at Paducah's Gaseous Diffusion Plant

DOE selected Fluor to manage the next phase of the cleanup at the Paducah Gaseous Diffusion Plant (GDP) in Paducah, Kentucky. Fluor is the prime contractor for the management, integration, and execution of the deactivation and post GDP shutdown remediation activities of the Paducah site.
2015
Savannah River Site employees design new, safe equipment to transport drums of nuclear material
&w=3840&q=75)
2015: Savannah River Site employees design new, safe equipment to transport drums of nuclear material
&w=3840&q=75)
The K Area Complex at Savannah River provides for the handling and interim storage of the United States’ excess plutonium and other special nuclear materials. It also fulfills the U.S. commitment to international nonproliferation efforts in a safe and environmentally sound manner.
Always looking for ways to complete work safely and more efficiently, employees of Savannah River Nuclear Solutions, a Fluor-led company, to develop a drum-management solution that minimizes exposure to nuclear material.
2015
PG&E names Fluor the integrated solutions supplier at Diablo Canyon Nuclear Power Plant

2015: PG&E names Fluor the integrated solutions supplier at Diablo Canyon Nuclear Power Plant

Fluor was awarded an operations and maintenance contract by Pacific Gas and Electric Company to serve as the integrated services supplier for the two-unit Diablo Canyon Power Plant in Avila Beach, California. Under the five-year contract, Fluor is responsible for site services, facility maintenance, strategic and station projects, engineering services and outage services at the Diablo Canyon facility.
2015
Fluor wins award for new technology employed at the Savannah River Site

2015: Fluor wins award for new technology employed at the Savannah River Site

The Savannah River Site has calculated more than $10 million in savings as a result of a new method for measuring the radioactivity of transuranic waste. The process improvement won Savannah River the DOE Sustainability Award in the category of Exemplary Practice.
2015
Pup, an innovative shipping container, used to transport hazardous material
&w=3840&q=75)
2015: Pup, an innovative shipping container, used to transport hazardous material
&w=3840&q=75)
The Fluor-led contracting team at the Portsmouth D&D facility shipped hazardous materials using an innovative, new transportation container called a “pup”. Pups are reusable overpack containers used to transport hazardous material. The waste contained in the pups is an ash byproduct from a flame tower used in the 1970s to improve recovery of uranium during the enrichment process.
2015
Fluor awarded five-year contract at Comanche Peak
&w=3840&q=75)
2015: Fluor awarded five-year contract at Comanche Peak
&w=3840&q=75)
In 2015, Fluor was awarded a five-year contract to provide engineering, maintenance and modifications, and facility services at Comanche Peak Nuclear Power Plant. Comanche Peak is Luminant’s sole nuclear generation asset. The plant operates two units which, combined, produce 2,300 MW of power.
Fluor’s relationship with Luminant began in 1984, providing ongoing maintenance and modification services at four fossil power plants. Fluor previously serviced the Comanche Peak plant from 1991 until 2006. The nuclear power plant is located in Somervell County, Texas.
2015
Fluor named by Westinghouse to manage construction of four U.S. nuclear power units
&w=3840&q=75)
2015: Fluor named by Westinghouse to manage construction of four U.S. nuclear power units
&w=3840&q=75)
Fluor was named by Westinghouse Electric Company, LLC (Westinghouse), to manage construction of two Westinghouse AP1000® nuclear power reactor projects in Georgia and South Carolina – owned and operated by Georgia Power and SCANA/Santee Cooper, respectively.
Fluor will manage a significant portion of the construction of Vogtle Electric Generating Plant’s Units 3 & 4 near Waynesboro, Georgia, and two additional nuclear electric generating units at the V.C. Summer Nuclear Generating Station located in Fairfield County, South Carolina. Fluor will be providing project execution and direction, accountability for and management of professional staff and craft personnel, and a focus on safety, quality, and project delivery certainty.
2016
DOE selects Fluor to support the Idaho Cleanup project

2016: DOE selects Fluor to support the Idaho Cleanup project

The DOE selected Fluor Idaho, LLC, to support the department's cleanup mission at the Idaho Site under the Idaho Cleanup Project (ICP) Core Contract. Fluor Idaho will focus on addressing the key elements of the ICP Core – dispositioning transuranic waste (TRU), spent nuclear fuel storage and high-level radioactive waste processing. This work will support multiple national and state regulatory agreements, including the 1995 Idaho Settlement Agreement, and to seamlessly consolidate the ICP and Advanced Mixed Waste Treatment Project contracts. The consolidation eliminates redundancies, integrates activities and ensures the government gets the highest return on its investment.
2016
Nuclear remediation underway for Magnox

2016: Nuclear remediation underway for Magnox

The Nuclear Decommissioning Authority (NDA) selected the Cavendish Fluor Partnership (CFP) to decommission 12 nuclear sites located throughout England, Wales, and Scotland. The Cavendish Fluor Partnership brings international decommissioning, operational, and site expertise to the project, with the objective of delivering the program safely and cost effectively. The Magnox decommissioning contract is a 13.5-year contract divided into two phases. The first phase is 6.5 years and valued at more than $3.6 billion. This contract is a strong “One Fluor” project, joining the talent of FGG nuclear decommissioning resources with the in-country capabilities of the Farnborough Office.
2016
Idaho National Laboratory site permit issued for NuScale small modular reactor project
&w=3840&q=75)
2016: Idaho National Laboratory site permit issued for NuScale small modular reactor project
&w=3840&q=75)
The DOE granted the Utah Associated Municipal Power Systems (UAMPS) a use permit to choose a suitable nuclear power plant site within the boundary of the Idaho National Laboratory site. UAMPS plans to build and operate the lead NuScale power plant.
The 110 year agreement period includes 10 years of licensing, site preparation and plant construction followed by 99 years of plant operation and retirement.
2017
Savannah River Nuclear Solutions operates Savannah River National Laboratory
&w=3840&q=75)
2017: Savannah River Nuclear Solutions operates Savannah River National Laboratory
&w=3840&q=75)
Savannah River Nuclear Solutions, LLC, a Fluor partnership, is responsible for the management and operations of the U.S. Department of Energy’s Savannah River National Laboratory (SRNL). SRNL focuses on three major initiatives: national security, environmental stewardship and clean energy.
2017
Fluor performs procurement and construction work for Ontario Power Generation's Darlington Nuclear Station refurbishment

2017: Fluor performs procurement and construction work for Ontario Power Generation's Darlington Nuclear Station refurbishment

Fluor was selected by Ontario Power Generation (OPG) for the procurement and construction of refurbishment work at OPG's Darlington Nuclear Generating Station in Ontario, Canada. Fluor's scope will include the replacement of emergency power generators for Units 1 and 2. The refurbishment will support an additional 30 years of low-cost, clean power for Ontario.
2018
NuScale’s SMR becomes first ever to complete U.S. Nuclear Regulatory Commission Phase 1 review
&w=3840&q=75)
2018: NuScale’s SMR becomes first ever to complete U.S. Nuclear Regulatory Commission Phase 1 review
&w=3840&q=75)
In April 2018, the U.S. Nuclear Regulatory Commission (NRC) announced it has completed the first and most intensive phase of review for NuScale Power’s design certification application. The Phase 1 review completion milestone signals NuScale’s momentum in bringing America’s first small modular reactor to market.
2019
Fluor provides management and operations services for Canadian Nuclear Laboratories

2019: Fluor provides management and operations services for Canadian Nuclear Laboratories

Canadian National Energy Alliance (CNEA), a Fluor consortium, was selected as preferred bidder to manage and operate Canadian Nuclear Laboratories (CNL). The contract focuses on three main priorities: addressing Atomic Energy of Canada Limited (AECL)’s radioactive waste and decommissioning responsibilities, delivering nuclear science and technology that supports the Government of Canada and industry and revitalizing the Chalk River Laboratories located in Ontario, Canada.
2020s
2020 and beyond.
2020
NuScale Power achieves U.S. Nuclear Regulatory Commission design certification

2020: NuScale Power achieves U.S. Nuclear Regulatory Commission design certification

In August 2020, Fluor announced that that NuScale Power, in which Fluor is the majority investor, received final design certification by the U.S. Nuclear Regulatory Commission (NRC). The certification achievement is expected to advance the commercialization of NuScale’s small modular nuclear reactor (SMR) technology.
2023
Fluor supports U.S. national security by constructing plutonium pit production facility at Savannah River Site
&w=3840&q=75)
2023: Fluor supports U.S. national security by constructing plutonium pit production facility at Savannah River Site
&w=3840&q=75)
Fluor serves as the engineering, procurement and construction management company that supports the U.S. Department of Energy’s (DOE) National Nuclear Security Administration (NNSA) in its objective to produce plutonium pits at the Savannah River Site (SRS) in Aiken, SC. The construction of the Savannah River Plutonium Processing Facility (SRPPF), which will produce the pits, is a directive from the NNSA and is one of the top projects within the Nuclear Security Enterprise today.
In support of the nation’s nuclear deterrent, the NNSA plans to make at least 80 pits per year in production facilities at SRS and Los Alamos National Laboratory in New Mexico. A pit is a critical component in every nuclear weapon.
2024
Fluor awarded small modular reactor FEED contract in Romania

2024: Fluor awarded small modular reactor FEED contract in Romania

Fluor signed a contract with RoPower Nuclear for Phase 2 front-end engineering and design (FEED) work at its small modular reactor (SMR) facility in Doicesti, Romania. Fluor completed Phase 1 FEED work in 2023.
The Phase 2 FEED work will customize a six-reactor SMR power plant with NuScale technology, capable of producing up to 462 megawatts to European codes and standards. Generating carbon-free power, the plant will mark a significant milestone in Romania’s advancement of clean energy initiatives.